基于施工便捷性的输电线路钢管杆优化设计

Optimal Design of Transmission Line Steel Pipe Poles Based on Construction Convenience

  • 摘要: 当前钢管杆的设计,主要考虑施工完成后能否满足运行要求,对施工过程中的便捷性考虑不足。文章从施工角度出发,对输电线路钢管杆进行针对性优化,通过增设专用吊装板、卡口定位结构及双层踏点挂钩,解决施工吊装不稳、杆段对接低效、人员作业无可靠踏点等实际难题。并通过关键构件(吊装板、双层挂钩)的荷载验算,验证了优化方案的承载安全性与施工可行性,可有效提升钢管杆安装效率、降低施工风险。

     

    Abstract: Current steel pipe pole design mainly focuses on whether operational requirements are met after installation, with insufficient consideration of construction convenience. From a construction perspective, this paper proposes targeted design improvements for steel pipe poles used in transmission lines. Dedicated hoisting plates, notched positioning structures, and double-layer foothold hooks are added to solve practical problems such as unstable hoisting, inefficient alignment of pole sections, and the lack of reliable footholds for workers. Load-bearing checks of key components, including the hoisting plates and double-layer hooks, verify the load-bearing safety and construction feasibility of the optimized design. The proposed design effectively improves the installation efficiency of steel pipe poles and reduces construction risks.

     

/

返回文章
返回