  • 摘要: 针对山区地形复杂、交通受限条件下10 kV配电线路施工效率低、安全风险高的问题,系统总结了4种机械化施工典型工法:微型桩基础施工工法、山地组合抱杆组塔工法、无人机展放导引绳工法和履带式运输与吊装工法。以国网北京延庆供电公司某山区10 kV线路工程为案例,对比分析了机械化施工与传统人工施工在工期、人工投入、安全指标和环境影响等方面的效益差异。结果表明:机械化施工使单位杆塔基础施工工期缩短45%,人工投入减少60%,高空坠落事故风险降低80%,林地扰动面积减少35%。综合全生命周期成本分析,机械化施工净现值比传统工艺高12.3%,投资回收期约3.2年。

     

    Abstract: To address the problems of low construction efficiency and high safety risks in 10 kV distribution line construction under complex terrain and limited transportation conditions in mountainous areas, this paper systematically summarizes four typical mechanized construction methods. These methods include the micropile foundation construction method, tower erection using combined gin poles in mountainous areas, UAV pilot rope deployment, and crawler transportation and hoisting. Taking a 10 kV line project in a mountainous area of State Grid Beijing Yanqing Power Supply Company as a case study, this paper compares and analyzes the benefits of mechanized construction and traditional manual construction in terms of construction period, labor input, safety indicators, and environmental impact. The results show that mechanized construction shortens the construction period of each tower foundation by 45%, reduces labor input by 60%, lowers the risk of high-altitude fall accidents by 80%, and reduces the disturbed forestland area by 35%. Based on life cycle cost analysis, the net present value of mechanized construction is 12.3% higher than that of traditional methods, and the payback period is about 3.2 years.

     

/

返回文章
返回