刚性台阶基础在输电线路绿色建造中的作用

The Role of Rigid Step Foundation in the Green Construction of Transmission Lines

  • 摘要: 为切实贯彻国家电网公司倡导的输电线路绿色建造理念,文章介绍了原状土掏挖基础面临的实际问题,比较了刚性台阶基础和柔性板柱基础在临界状况下的经济性,从而提出了刚性台阶基础在35~110 kV输电线路直线塔基础中不可或缺的观点;根据工民建专业有关放坡规定和几十年的现场施工经验,建议松砂石坑3.0 m以内的基坑,去除厚1.0 m左右的表层土后,取消操作裕度和放坡;对刚性台阶基础底板采取满灌施工工艺,减少土石方量开挖和基础混凝土、钢筋用量以及支模板工序,大幅提高基础抗拔力或减少基坑深度,有效解决了原状土掏挖基础机械开挖的地形限制和强风化岩层嵌固基础人工开挖困境。

     

    Abstract: In order to effectively implement the concept of green construction of transmission lines advocated by State Grid Corporation of China, this paper introduces the practical problems faced by undisturbed soil excavation foundation, compares the economy of rigid step foundation and flexible plate column foundation under critical conditions, and puts forward the view that rigid step foundation is indispensable in the foundation of 35 ~ 110kV transmission line straight tower. According to the relevant grading regulations of civil engineering specialty and decades of on-site construction experience, it is suggested that the operation margin and grading should be cancelled after removing the surface soil with a thickness of about 1.0 m for the foundation pit within 3.0 m of loose sand and gravel pit. The full-filling construction technology is adopted for the rigid step foundation slab, which reduces the excavation of earth and stone, the amount of foundation concrete, steel bar and the process of supporting formwork, greatly improves the foundation pull-out force or reduces the depth of foundation pit, and effectively solves the terrain limitation of mechanical excavation of undisturbed soil excavation foundation and the artificial excavation dilemma of embedded foundation in strongly weathered rock stratum.

     

/

返回文章
返回