SHANG Jiacheng. Treatment and Analysis of SF6 Gas Leakage of 110 kV Gas Insulated Substation[J]. RURAL ELECTRIFICATION, 2023, (7): 78-79. DOI: 10.13882/j.cnki.ncdqh.2023.07.021
Citation: SHANG Jiacheng. Treatment and Analysis of SF6 Gas Leakage of 110 kV Gas Insulated Substation[J]. RURAL ELECTRIFICATION, 2023, (7): 78-79. DOI: 10.13882/j.cnki.ncdqh.2023.07.021

Treatment and Analysis of SF6 Gas Leakage of 110 kV Gas Insulated Substation

  • The 110 kV combined electrical equipment in a substation has air leakage problem. After the maintenance personnel carried out SF6 live air supply for it, combined with the site situation, they applied a variety of leak detection technologies to find the leak point, found the cause of air leakage of the combined electrical GIS equipment and proposed a solution, which thoroughly solved the air leakage problem of the combined electrical equipment gas chamber, avoided the occurrence of equipment accidents caused by long-term SF6 gas leakage, and ensured the safe and stable operation of the equipment.
  • loading

Catalog

    Turn off MathJax
    Article Contents

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return